The Lincoln Avenue construction project between S. 93rd Street and S. 97th Street is shifting into Phase 3. Traffic will use the newly constructed area while the southeast portion of the project begins reconstruction. The traffic control pattern is scheduled to change on Sept. 16. The new pattern is shown in the map below, and the detour is listed below. After the new traffic control is set up, sanitary sewer and water main work will begin on the new section.
Detours are as follows:
The Lincoln detour will be on 92nd Street, Cleveland Avenue, and 108th St. (HWY 100).
The National detour will be on Lincoln and 108th (Hwy 100).
This is not a City project. This project is run by the Wisconsin Department of Transportation. More information can be found at the Lincoln Avenue Construction page.